Soft-Story Retrofit Order Dismissal
Last updated: August 27, 2026
What are the official close-out requirements?
Per Ordinance 183893, two official close-out items dismiss the Order:
| Close-out requirement | Ordinance section | Who provides it |
|---|---|---|
| County Recorder certificate | §91.9306.6 | Department files with County Recorder |
| Statement on the approved plans | §91.9310.2 | California civil or structural engineer or architect (§91.9305.1) |
How does the close-out process work?
After construction completion, the design professional puts a statement on the approved plans per §91.9310.2. The Department then files a County Recorder certificate per §91.9306.6. These two official close-out items dismiss the Order.
Frequently asked questions
What is required to dismiss a soft-story retrofit Order?
Per Ordinance 183893, the Department files a County Recorder certificate (§91.9306.6) and the design professional (a California civil or structural engineer or architect per §91.9305.1) puts a statement on the approved plans (§91.9310.2) to dismiss the Order to Comply.
How long does Order dismissal take?
Dismissal timing depends on LADBS workload and completion of the official close-out requirements. Owners should complete construction and coordinate with the design professional promptly to avoid ordinance deadline violations.