LA Soft-Story Retrofit Completion

Per Ordinance 183893, completion occurs when the Department files a County Recorder certificate (§91.9306.6) and the design professional (a California civil or structural engineer or architect per §91.9305.1) puts a statement on the approved plans (§91.9310.2). These official close-out items dismiss the Order to Comply.

Last updated: August 27, 2026

What are the official close-out requirements?

Per Ordinance 183893, two official close-out items dismiss the Order:

Close-out requirementOrdinance sectionWho provides it
County Recorder certificate§91.9306.6Department files with County Recorder
Statement on the approved plans§91.9310.2California civil or structural engineer or architect (§91.9305.1)

What happens after completion?

After LADBS dismisses the Order, the building is no longer listed as noncompliant under Ordinance 183893. The owner retains completion records for future property transfers and lender inquiries.

Frequently asked questions

What marks LA soft-story retrofit completion?

Per Ordinance 183893, completion occurs when the Department files a County Recorder certificate (§91.9306.6) and the design professional (a California civil or structural engineer or architect per §91.9305.1) puts a statement on the approved plans (§91.9310.2).

Is the lender PML/SEL part of completion?

No. The PML (Probable Maximum Loss) or SEL (Scenario Expected Loss) is a Freddie Mac multifamily real estate appraisal for the lender's earthquake collateral risk assessment per ASTM E2026. Per Ordinance 183893, the Department files a County Recorder certificate (§91.9306.6) and the design professional puts a statement on the approved plans (§91.9310.2) to dismiss the Order, not lender underwriting documents.