An Order to Comply is issued to owners of soft-story buildings that fail to meet Ordinance 183893 seismic standards. The Order mandates retrofit completion by a deadline. Per the ordinance, the Department files a County Recorder certificate (§91.9306.6) and the design professional (a California civil or structural engineer or architect per §91.9305.1) puts a statement on the approved plans (§91.9310.2) to dismiss the Order.

Last updated: August 27, 2026

Why is the Order issued?

LADBS issues Orders to Comply to owners of wood-frame buildings with soft, weak, or open-front walls at the ground story. Ordinance 183893 requires these buildings to be seismically retrofitted. The Order notifies the owner of the compliance requirement and deadline.

Order componentDescription
Building identificationAddress and soft-story classification
Ordinance citationOrdinance 183893 requirements
Compliance deadlineDate by which retrofit must be completed
Required actionsSubmit proof/plans, obtain permit, complete construction
Enforcement informationContact LADBS for enforcement procedures

What are the compliance timelines?

Per dbs.lacity.gov, the property owner must comply with the ordinance within the following time limit from the receipt of the Order to Comply: 2 years: Submit proof of previous retrofit, or plans to retrofit or demolish; 3.5 years: Obtain permit to start construction or demolition; 7 years: Complete construction. Contact LADBS for enforcement information.

Deadline from receipt of Order to ComplyRequirement
2 yearsSubmit proof of previous retrofit, or plans to retrofit or demolish
3.5 yearsObtain permit to start construction or demolition
7 yearsComplete construction

Source: DBS Soft Story Retrofit Program

Frequently asked questions

What is an LADBS noncompliant building Order?

An LADBS Order to Comply is issued to owners of soft-story buildings that do not meet Ordinance 183893 seismic retrofit requirements. The Order mandates retrofit completion by a specified deadline. Contact LADBS for information on enforcement procedures.

How is the Order dismissed?

Per Ordinance 183893, the Order is dismissed when the Department files a County Recorder certificate (§91.9306.6) and the design professional (a California civil or structural engineer or architect per §91.9305.1) puts a statement on the approved plans (§91.9310.2).